Facility Restorations

Repair or Replacement

Key Points

1.  Repair cost includes only those  repairs, including non-emergency mold remediation, associated with the  damaged components and the codes and standards that apply to the repair of  the damaged components. The cost does not include upgrades of other components triggered by codes and  standards, design associated with upgrades, demolition of the entire  facility, site work, or applicable project management costs. The cost of  contents and hazard mitigation measures is not included in the repair  cost.
   2.  Replacement cost includes the costs  for all work necessary to provide a new facility of the same size or design  capacity and function as the damaged facility in accordance with all current  applicable codes and standards. The cost does not include demolition, site work, applicable project management  costs, cost of contents, and hazard mitigation measures.
   References:   Section 406(a) of the Stafford Act 44 CFR §206.226(f)
   Eligibility of Facilities for Replacement (The  50% Rule), FEMA Policy 9524.4, dated September 24, 1998
   Public Assistance Guide, FEMA 322, pages 36-38,  83


Detailed Discussion

FEMA will restore an eligible facility to its pre-disaster design. Restoration is divided into two categories: Repair or Replacement. If a facility is damaged to the point where the applicant thinks the facility should be replaced rather than repaired, the following calculation, known as the “50% Rule,” should be used to determine whether replacement is eligible. The repair cost does not include codes and standards upgrades, demolition, site work, or applicable project management costs.

IF          Repair Cost1

Replacement Cost2

     Repair Cost1

IF   Replacement Cost2

<    50% THEN only the repair cost is eligible

≥   50% THEN the replacement cost is eligible

1. Repair cost includes  only those repairs,  including non-emergency mold remediation, associated  with the damaged components and the codes and standards that apply to the repair of the damaged components.

The cost does not include upgrades of other components triggered by codes and standards, design associated  with upgrades, demolition of the entire facility, site work, or applicable project management costs. The cost of contents and hazard  mitigation measures  is not included in the repair cost.

2. Replacement cost includes  the costs for all work necessary to provide a new facility of the same size or design capacity and function as the damaged facility in accordance with all current applicable codes and standards. The cost does not include demolition, site work, applicable project management costs, cost of contents, and hazard  mitigation measures.


Related Guidance Categories

This website  is intended as a national source of information about  the delivery of  financial recovery services. It includes resources on eligibility, procurement, grant management delivery, and issues related to various Federal Programs currently supporting FEMA  Public Assistance program  financial recovery for governments and non-profits. This website is not affiliated or endorsed or sponsored  by  FEMA  or any other Federal grant program. The information provided in various webpage documents is derived largely from Federal  published materials. In general, under section 105 of the Copyright Act, such works are not entitled to domestic copyright protection under U.S. law and are therefore in the public domain.  The goal is to help navigate the various Federal websites and summarize grant information and requirements. It does not constitute legal advice or grant management advise and is provided for general informational purposes only. Only the Federal Agency responsible for grants can make determinations on eligibility and grant amounts. You should consult with your professional services advisors and State and Federal Grant Coordinators for more detailed guidance on specific FEMA Public Assistance financial recovery issues.

Please review the Terms of Use and Disclaimers and your continued use confirms your acceptance