44 C.F.R. 206.204(d)(2) provides that if FEMA denies a time extension request; the applicant may still be reimbursed for eligible project costs; but only those incurred up to the latest approved completion date.The Applicant completed the original approved $29;366.84 in repair work after the latest approved project completion date; and so those costs are not eligible for reimbursement.
PA Guide; at 110; 138-140.Nashville-Davidson Cnty.; FEMA-1909-DR-TN; at 4. Headnotes44 C.F.R. § 206.204(d)(2) provides that if FEMA denies a time extension request; the applicant may still be reimbursed for eligible project costs; but only those incurred up to the latest approved completion date.The Applicant completed the original approved $29;366.84 in repair work after the latest approved project completion date; and so those costs are not eligible for reimbursement.