Procurement
Procurement Costs/ Reasonable Costs/ PNP/ 705(c)
Community Action Program Committee; Inc
<<RETURN

Per 2 C.F.R. 215.44(c); “the ‘cost plus a percentage of cost’ and ‘percentage of construction cost’ methods of contracting shall not be used.”The Applicant entered into a non-compliant CPPC.

Procurement & Contracting Requirements
2018

PA Guide; at 28-31; 34.FP-205-081-2; Stafford Act Section 705; Disaster Grant Closeout Procedures; at 1; 4-7.Muschany v. United States; 324 U.S. 49; 61-62 (1944).Chambers Cty.; FEMA-1791-DR-TX; at 6 (May 26; 2017).St. Mary’s Acad.; FEMA-1603-DR-LA; at 2 (June 22; 2017). HeadnotesPer 2 C.F.R. § 215.44(c); “the ‘cost plus a percentage of cost’ and ‘percentage of construction cost’ methods of contracting shall not be used.”The Applicant entered into a non-compliant CPPC.

<<Open FEMA PA Appeal Link