FEMA may fund the costs of repairing; restoring; reconstructing; or replacing an eligible PNP facility on the basis of the design; function; and capacity of the facility as it existed immediately prior to the major disaster.The Applicant included multiple items of work/components in the SOW that were not required by any applicable code or standard; as such FEMA appropriately deobligated.
PA Guide; at 34; 75; 115.FP 205-081-2; at 4-7.St. Tammany Par. Sch. Bd.; FEMA-1603-DR-LA; at 6.Public Assistance Cost Estimating Format for Large Projects; Instructional Guide; Version 2; at 10.HeadnotesFEMA may fund the costs of repairing; restoring; reconstructing; or replacing an eligible PNP facility on the basis of the design; function; and capacity of the facility as it existed immediately prior to the major disaster.The Applicant included multiple items of work/components in the SOW that were not required by any applicable code or standard; as such FEMA appropriately deobligated.