Pursuant to DAP9526.1 and the PA Guide; when an applicant requests an improved project that will replace the facility; the cost of mitigation measures are not eligible. FEMA approved an improved project as requested by the Applicant. The requested project completely replaced the steam system. Accordingly; mitigation measures are not eligible for funding.
DAP9526.1; at 4.PA Guide; at 110-111.FEMA Second Appeal Analysis; Florida Department of Transportation; FEMA-4068-DR-FL; at 3 (Aug. 5; 2016).FEMA Second Appeal Analysis; Florida Department of Transportation; FEMA-1785-DR-FL; at 3 (July 9; 2016).HeadnotesPursuant to DAP9526.1 and the PA Guide; when an applicant requests an improved project that will replace the facility; the cost of mitigation measures are not eligible. FEMA approved an improved project as requested by the Applicant. The requested project completely replaced the steam system. Accordingly; mitigation measures are not eligible for funding.