44 C.F.R. 206.223(a)(1) requires that work must be required as a result of a disaster. 44 C.F.R. 206.226 states; eligible facilities must be restored to the design; function; and capacity that existed immediately prior to the disaster.The Applicant did not demonstrate that the repairs made to the structures were not present prior to the disaster.44 C.F.R. 206.226(d) states; any costs associated with work that changes the predisaster construction of a facility may be eligible as codes or standards
City of Sweetwater; FEMA-1345-DR-FL; at 3 (Aug. 15; 2017).The Opportunity Center; FEMA-1539-DR-FL; at 6 (Dec. 22; 2016).Lockwood Irrigation District; FEMA-1996-DR-MT; at 2 (Jan. 16; 2014). Headnotes 44 C.F.R. § 206.223(a)(1) requires that work must be required as a result of a disaster. 44 C.F.R. §206.226 states; eligible facilities must be restored to the design; function; and capacity that existed immediately prior to the disaster.The Applicant did not demonstrate that the repairs made to the structures were not present prior to the disaster.44 C.F.R. § 206.226(d) states; any costs associated with work that changes the predisaster construction of a facility may be eligible as codes or standards