44 C.F.R. 206.204(d)(2) provides the authority for the Regional Administrator to grant or deny time extension requests. 44 C.F.R. 206.204(c)(2)(ii) indicates that the Grantee can grant a time extension request if the applicant shows “extenuating circumstances or unusual project requirements beyond the control of the subgrantee.â€
44 C.F.R. § 206.204(c)(2)(ii)Town of Fairfax; FEMA-1046-DR-CA (June 7; 1999).Harding University; FEMA-1472-DR-AR (Dec. 7; 2004).Headnotes44 C.F.R. § 206.204(d)(2) provides the authority for the Regional Administrator to grant or deny time extension requests. 44 C.F.R. § 206.204(c)(2)(ii) indicates that the Grantee can grant a time extension request if the applicant shows “extenuating circumstances or unusual project requirements beyond the control of the subgrantee.”