Facility Restoration
Buildings/ Scope of Work
University of Houston-Main Campus
<<RETURN

Per 44 C.F.R. 13.30(d)(1); an applicant must obtain FEMA approval prior to revising the SOW.All items of work on appeal exceeded; or were additions to; what was listed in the approved SOW on PW 5800.

Change in Scope of Work
2017

Public Assistance Guide; at 33; 140.Lawrence County Engineer; FEMA-4002-DR-OH; at 6. HeadnotesPer 44 C.F.R. § 13.30(d)(1); an applicant must obtain FEMA’s approval prior to revising the SOW.All items of work on appeal exceeded; or were additions to; what was listed in the approved SOW on PW 5800.