FEMA may approve Alternate Projects based on an eligible project SOW. Engineering services to determine the type and extent of repairs necessary to return a facility to its predisaster condition are generally eligible; but only as part of the overall restoration project. FEMA may reimburse project expenses incurred before the project deadline but only if the project is completed.At the time the Applicant submitted its Alternate Project request; the approved SOW only included A&E services. However; the Applicant did not submit a SOW to repair the Facility and therefore; there is no approved SOW for restoration of the Facility or an approved cost estimate upon which to base an Alternate Project. Accordingly; FEMA cannot approve the Applicant Alternate Project request.The Applicant had no eligible SOW upon which FEMA could base approval of an Alternate Project. In addition; because the Applicant did not restore the Facility; the engineering costs are ineligible. Therefore; FEMA denies the appeal.
HeadnotesFEMA may approve Alternate Projects based on an eligible project SOW. Engineering services to determine the type and extent of repairs necessary to return a facility to its predisaster condition are generally eligible; but only as part of the overall restoration project. FEMA may reimburse project expenses incurred before the project deadline but only if the project is completed.At the time the Applicant submitted its Alternate Project request; the approved SOW only included A&E services. However; the Applicant did not submit a SOW to repair the Facility and therefore; there is no approved SOW for restoration of the Facility or an approved cost estimate upon which to base an Alternate Project. Accordingly; FEMA cannot approve the Applicant’s Alternate Project request.ConclusionThe Applicant had no eligible SOW upon which FEMA could base approval of an Alternate Project. In addition; because the Applicant did not restore the Facility; the engineering costs are ineligible. Therefore; FEMA denies the appeal.