DAP 9523.3 states that FEMA may grant time extensions based on documentation showing: (1) circumstances beyond the Applicant’s control that prevented completion of the reconstruction project within the initial time limit, (2) status of the permanent restorative work, and (3) revised timeline for project completion. The circumstances that the Applicant states were beyond its control, do not justify its delay in completing the approved repair work to the hospital. Since the Applicant has not made significant progress toward effectuating the repair work approved in PW 718, and the estimated time to complete the authorized work has elapsed, FEMA denies the request for additional time extensions for PWs 828 and 1106.
The Applicant has not demonstrated circumstances beyond its control prevented completion of PW 718’s approved SOW. Accordingly, FEMA denies the appeal for additional time extensions for PWs 828 and 1106.
Stafford Act § 403(a)(3)(D). 44 C.F.R. § 206.204, 206.225, 206.226. Public Assistance Guide, FEMA 322, at 32. DAP 9523.3, Provision of Temporary Relocation Facilities. Hancock County Board of Supervisors, FEMA-1604-DR-MS; City of Springfield, FEMA-1994-DR-MA; Williamsburg Regional Hospital, PW 718, FEMA-4241-DR-SC; City of Tallahassee, FEMA-1785-DR-FL.