When equipment purchased with PA funding is no longer needed for response to or recovery from the incident, the applicant must calculate the FMV of equipment that has a current FMV of $5,000 or more, and FEMA reduces eligible funding by this amount. The date used to determine when equipment is no longer needed is based on the work completion deadline of May 11, 2023, or information previously provided by an applicant. The Applicant did not calculate the FMV of its ambulance purchased with PA funding; therefore, FEMA calculated the FMV based on the four-month time frame the equipment was used for eligible work, and the Applicant has not substantiated that the ambulance was used for eligible work beyond that time frame.
The Applicant has not demonstrated that it used its ambulance for eligible medical transports related to COVID-19 beyond the four-month time frame used by FEMA to calculate the FMV of the ambulance. Thus, the appeal is denied.
Stafford Act § 403(a)(3). 44 C.F.R. §§ 206.223(a)(1), 206.225(a); 2 C.F.R. § 200.313(c), (e)(2). PAPPG, at 29, 133. Disposition Requirements FAQs, V.2, at 2, 4; Medical Care Policy, at 3-5. City of Atlanta, FEMA-4501-DR-GA, at 4 (Apr. 26, 2024).