Direct Administrative Costs & Management Costs

Administrative Costs

HEADNOTES

CONCLUSION

Based on the Applicant’s latest non-management costs project work completion date, March 10, 2022, FEMA cannot extend the timeframe for the Applicant to claim management costs incurred beyond September 6, 2022. Therefore, this appeal is denied.

AUTHORITIES

Direct Administrative Costs & Management Costs