Change in Scope of Work

Scope of Work

HEADNOTES

CONCLUSION

The Applicant’s repair method addressed hidden disaster-related damage and represents the least costly approach to restore the Facility to its predisaster design and function. Therefore, this appeal is approved for $183,272.00.

AUTHORITIES

Change in Scope of Work